Dalton officials curtail Town Hall renovation after costs double | Central Berkshires

DALTON — Officials in Dalton had been already mixed about asking taxpayers to kick in an additional $100,000 up coming 7 days for a Town Hall renovation.

Let’s not request citizens once more just after this, Select Board Chair Joe Diver explained to colleagues early this thirty day period.

On Tuesday, the board held to that, selecting to radically scale the venture back again, in the experience of a unexpected doubling in its price tag.

Until eventually just lately, function to take out asbestos from the attic of the historic Carson Avenue creating, combined with the will need to take out bats and make other modifications, known as for an investment decision of about $600,000 — with all but a sixth of that previously OK’d by voters.

To start with it was bats and bigger asbestos-removal expenses driving up the cost.

Now, it is a point out law.

Town Supervisor Thomas Hutcheson advised the board Tuesday that the renovations planned now involve installation of an elevator, right after it was discovered that the improved charge of the get the job done triggered a provision in condition law.

Just before, officials assumed supplying accessibility through set up of an elevator could hold out.

&#13
After paying $30,000 to evict bats, a Dalton Town Hall project needs help to take flight

Hutcheson cited an error in early measures of the renovation, telling the board that somebody ought to have detected that a challenge of the scale envisioned would have obligated the town to provide handicap access.

“That’s really a great deal drinking water underneath the bridge,” Hutcheson reported.

A state law waives that necessity for function that is either beneath $100,000, or less than 30 per cent of a building’s worth, according to Diver.

With freshly uncovered costs, the renovation was poised to climb from $600,000 to $1.3 million.

The 5-member board voted unanimously to scale back again the perform to what had been proposed years ago: asbestos removal in the building’s attic place, which some connect with the “opera home.”

“I imagine we want to faucet the brakes,” stated member Daniel Esko. “No a single really is aware what this will value if we commence. I’m not supportive of ongoing funding without an close in sight.”

Member John Boyle questioned the additional $700,000 in charges outlined by Hutcheson. Of that, Hutcheson estimated that providing an elevator would expense practically $500,000. On leading of that, new facts reported the task would demand practically $200,000 in additional building expenses to deconstruct and rebuild partitions on the building’s next floor, to allow them to support better weight from earlier mentioned.

However a further price: The wallboard joint compound employed in the second-ground partitions incorporates 2 p.c asbestos, Hutcheson stated. A point out Office of Environmental Security rule usually means that the wall content taken aside would have to be dealt with as a much more costly asbestos abatement.

Boyle stated he believed the estimate on the elevator price — almost $500,000 — was minimal. “We should genuinely seem askance at that determine. I feel it is nearer to a million,” he explained.

Although Hutcheson proposed getting the desired $700,000 in added funding from two wet day accounts, William Drosehn, chair of the Finance Committee, urged the board not to deplete all those funds.

Drosehn reported the scope of the venture expanded above time, which may well have led officials not to anticipate the want to comply with the state law’s handicap accessibility prerequisite.

At a benefit of $2 million, that requirement for the City Corridor is invoked for a task that exceeds $600,000. The new costs would press it properly above that.

&#13
Bats are making Dalton’s Town Hall their personal B&B. The town gets the bill and has to pause renovations

“It seems to me to be an overreach,” Drosehn advised the board from the viewers at the senior heart, referring to additional modern elements of the challenge that provided generating operate space on the upper flooring. “This was never, as I recall, thought of to be employed as place.”

“We want to be fantastic stewards of the taxpayers’ money,” member Marc Strout claimed.

At a unique city meeting June 27, a warrant posting looking for $100,000 in new funding will be tabled, officers stated.

Alternatively, the board approved a program to remove asbestos insulation in the attic, content which is been fouled and designed even extra harmful by bat feces, working with revenue now allotted. Then, the undertaking would merely seal off the building’s third floor for now.

Right after that, the board ideas to start off in new on talks about town place of work house demands and how they can most effective be fulfilled.